Energy Resilience in Action: CCHP

Recovery for a $67M University Village

An off-campus facility that houses 650 students in a $67 million mixed-use village on a 34-acre parcel of land is an
innovative public-private partnership between a Mississippi D-1 university and the largest apartment property manager in
the U.S. These partners, as a part of their clean energy infrastructure project, had a Combined Cooling, Heat and Power
(CCHP) designed and installed.

The Goal

Operate a centralized heating and cooling plant that runs efficiently and economically to provide HVAC and electricity to the entire complex with maximum resiliency in the event of grid failure. The energy consultants working with the partnership contacted CoolSys when the unit was inoperable at start up.

The Problem

An in-depth inspection by CoolSys of the CCHP equipment identified areas requiring additional integrations and upgrades prior to start-up and then commissioning of the inoperable cogeneration unit.

Though the partnership had numerous goals, they did not have adequate internal resources to properly maintain the new equipment and achieve their efficiency and sustainability goals.

Front outside view of an off campus building.

The Solution

The CoolSys Energy Solutions team stepped in to address the property’s challenges, employing a multifaceted approach to assess, repair, customize, commission, monitor the systems 24/7/365, and maintain to prevent further outages and inefficiencies.

Key Actions

Diagnostics & Issue Resolution

CoolSys CoGen specialists conducted a thorough technical assessment of the systems, pinpointing the root causes of the integration errors and inefficiencies in the overall system.

24/7/365 Monitoring & Real-Time Response

Once the CCHP unit was commissioned, CoolSys Energy Solutions implemented 24/7/365 monitoring and maintenance services for the College View.

Commissioning & System Upgrades

CoolSys customized and commissioned the CCHP unit for enhanced operability. By calibrating it to work in optimal balance with the absorption chiller, external radiators and existing boilers, we achieved seamless performance.

Preventive Maintenance Implementation

CoolSys introduced a comprehensive preventive maintenance program covering all system components. This included regular inspections, calibration, and predictive replacements to prevent future failures.

The Results

The results of CoolSys CoGen’s commissioning, monitoring and service were transformational for the client organization. Addressing both the immediate and long-term inefficiencies, the facility experienced measurable improvements across key performance indicators. The success of this project strengthened the client’s trust in CoolSys. Recognizing the value and reliability delivered, the property managers have extended CoolSys’ maintenance and monitoring services for five additional years. This expansion further underlined CoolSys’ position as a trusted partner in ensuring operational excellence.

Optimized Operations

The CCHP system now operates at an impressive 98%+ availability year after year, while delivering more than 42,000 operational hours of resilient, efficient power to the property consistently and reliably.

Environmental Impact

By optimizing the system’s energy use the off-campus student housing complex significantly reduced its greenhouse gas (GHG) emissions by 39%, reinforcing its commitment to environmental sustainability.

Elevated Resilience & Real Time Response

By properly calibrating and maintaining the systems, the CHP units exceeded the projections with 98%+ resiliency. The monitoring and service played a vital role during an emergency on-site situation ensuring students had domestic hot water, HVAC heat and operating elevators without interruption at a crucial time.

Improved Energy Efficiency & Cost Savings

The facility reduced costs by $200,000 annually totaling $1.2M over the 6 years the systems have been under CES care.

For this reason, the client has decided to extend the agreement for an additional 5 years.

Customer Testimonial

Project Highlights

Uptime/Increased Resilience

0 %

Cost Reduction

$ 0 M

Reduction in GHG Emissions

0 %

Unit Operational Hours

0 +

Optimize Your Facilty with CoolSys

Ready to cut costs, boost resilience, and lower emissions? Discover how CHP, CoGen, and Multi-Energy Solutions from CoolSys can power your business efficiently.

Related Reading

Innovative Power and Full-stack Solutions for Data Centers Our expert team brings together best-in-class engineering, full-stack cooling and power equipment,

An off-campus facility that houses 650 students in a $67 million mixed-use village on a 34-acre parcel of land is

CHP Energy Savings Calculator In just a few clicks, quantify the financial savings, energy reduction and environmental benefits combined heat

Comprehensive energy solution helps save data center 100% on energy costs

CoolSys's comprehensive energy solutions and CHP systems help a data center save 100% on energy costs. Learn more

Questions? Need Service?

We're Here to Help

Reach us directly for service requests at 866-417-6586, or fill out the form . Our team is ready to respond swiftly and answer any questions you may have.

Questions? Ready to Get Started?

Let’s Move Forward. Together.

Discover the advantages of aligning with the foremost authority in HVAC and refrigeration services. As a partner steeped in industry knowledge, we’re dedicated to elevating you, your team and your business. Learn More about our acquisition process and benefits, or fill out the form below.

This Website Uses Cookies.

We use Cookies to offer you a better browsing experience, analyze site traffic, personalize content, and serve targeted advertisements. More information can be found here. We do not sell or share your information with any third parties. By continuing to browse Coolsys.com you will consent to our use of cookies.