CO2 refrigeration system

CASE STUDY

Nationwide CO2 Refrigeration on Accelerated Schedules

Our customer, a major food distribution operator, manages fresh and frozen food distribution zones embedded within existing fulfillment centers to support rapid local delivery.

These cold environments must meet strict temperature requirements, deliver high uptime, and open precisely on scheduled launch dates tied directly to market-facing commitments.

The Problem

Delivering Advanced CO2 Refrigeration and Controls—On Compressed, Non-Negotiable Timelines

As the major food distribution operator expanded its fresh and frozen food offerings, it standardized on Transcritical CO2 refrigeration systems to align with long-term sustainability goals, refrigerant compliance, and energy efficiency objectives. The customer also required a single, reliable partner capable of installing CO2 refrigeration systems, all refrigerated cases, and customized control systems consistently across multiple sites and states.

A critical operational requirement was the use of hot gas defrost utilizing waste heat from the CO2 systems, rather than traditional electric defrost. Hot gas defrost offers clear advantages—lower energy consumption, reduced strain on rapidly growing electrical demand, faster defrost cycles, improved temperature stability, and increased overall system efficiency. However, the controls platform selected for these facilities did not natively support hot gas defrost from Transcritical CO2 systems.

This created a significant technical gap. General contractors engaged multiple vendors to address the issue, but proposed solutions proved incomplete, unreliable, or incompatible with the customer’s standardization requirements. 

Without a viable technical path forward, the refrigeration scope posed a direct risk to performance, consistency, and commissioning timelines.

Compounding the challenge, the customer needed to open six sites across four states on fixed, non-negotiable dates, aligned with scheduled advertising campaigns promoting fast local delivery of fresh food. These immovable launch dates compressed construction schedules by 30–60 days, leaving no margin for redesign, rework, or delays.

With no solution in place and opening dates approaching, they escalated the issue and engaged CoolSys to deliver a solution that could meet both the technical requirements and the accelerated schedule.

The Solution

End-to-End CO2 Refrigeration, Controls Customization, and Schedule-Driven Execution

CoolSys delivered a fully integrated, end-to-end solution, serving as a single point of accountability across refrigeration installation, controls customization, and program execution.

CO2 Refrigeration & Refrigerated Case Installation

CoolSys installed the transcritical CO2 refrigeration systems and all refrigerated cases within their fresh and frozen distribution zones. This ensured proper integration between racks, evaporators, piping, and cases while eliminating handoff risk between multiple contractors.

System installation was sequenced to support accelerated construction timelines without compromising quality or safety.

Equipment Specs

12

Transcritical CO2 systems installed/started

66

Evaporator coils hung and piped

133

Valve stations set and piped

485

Glass doors set, started and turned over on time

Controls Customization for Hot Gas Defrost

CoolSys engineers customized and reprogrammed the refrigeration control systems to enable hot gas defrost using waste heat from the CO2 systems.

Compressed refrigerant vapor was safely diverted from the low- and medium-temperature compressor discharge to the evaporators during defrost cycles.

Key technical elements included:

  • Advanced defrost logic tailored for transcritical CO2 operation
  • Pressure management for systems operating at up to 120 bar
  • Integration of additional solenoid valves, check valves, and pressure regulators
  • Use of CO2-rated components and steel piping where required

The solution delivered:

  • 10–15 minute defrost cycles
  • Thermal defrost efficiency between 34.8% and 50%
  • COP improvements of up to 8.5% compared to electric defrost
  • Improved product temperature stability during defrost events
  • Alleviate rapid electricity demand

Measurements

6,843 ft

EMS conduit

78,744 ft

EMS cabling

51,242

Copper pipe installed, welded and pressurized

Program Management & OEM Coordination

The CoolSys Program Management Group diligently managed every aspect of the construction effort, coordinating installation teams, energy and controls specialists, and refrigeration and controls OEMs.

Close collaboration with general contractors ensured alignment across equipment procurement, installation sequencing, controls integration, commissioning, and startup.

To meet the customer’s aggressive timelines, CoolSys established a scalable national delivery framework that intentionally incorporated the 30–60 day schedule compression.

This framework standardized installation practices, controls programming, commissioning procedures, and quality controls—allowing CoolSys to execute multiple sites in parallel without sacrificing consistency or performance.

Engineering Confidence into Every System

CoolSys’ deep expertise in CO2 refrigeration, controls engineering, and large-scale deployment ensured these challenges were addressed safely, reliably, and repeatably.

The Impact

On-Time Openings, Reduced Risk, and a Scalable National Standard

The integrated solution delivered clear operational and business results:

  • Six complex refrigeration systems delivered across four states, on time and on schedule
  • Enabled high-efficiency hot gas defrost using CO2 waste heat
  • Reduced energy use versus electric defrost while improving temperature stability
  • Absorbed 30–60 days of schedule compression without compromising quality or safety
  • Ensured they could deliver fresh food to local markets exactly as advertised
  • Established a repeatable national standard for future deployments

 

As a direct outcome of this success:

  • The customer contracted CoolSys to complete 11 projects in 2025
  • An additional 8 projects are scheduled for 2026, expanding the solution nationwide

Conclusion

By serving as a single nationwide partner capable of installing transcritical CO2 refrigeration systems, refrigerated cases, and customized controls, CoolSys enabled the food distribution operator to deploy a high-efficiency hot-gas defrost strategy under accelerated construction schedules.

The results were improved energy performance, lower energy consumption, reduced execution risk, and on-time facility openings aligned with market launch commitments—establishing a scalable blueprint for future fresh and frozen distribution centers.

Project Highlights

$15.9 M

Worth of Work Completed on a Compressed Schedule

7,315 hrs

EMS labor

19,810 hrs

Refrigeration labor

7,265 hrs

Subcontract work