When BSM Construction received approval to build a new Phoenix-area location for a leading specialty grocery retailer, they faced a tight schedule, CO2 refrigeration complexity and a fixed grand opening date that could not shift. They needed a refrigeration partner capable of delivering a full turnkey installation—including a complete Acorn Evac vacuum plumbing system—under fast-track conditions.

CoolSys delivered the entire refrigeration and controls scope, including piping, insulation, rack installation, Hill Phoenix case installation, EMS controls, start-up, commissioning and installation of the Acorn Evac vacuum waste system used for case drainage. Despite delays and shifting timelines, CoolSys kept the project on track and ensured the store opened on time—with record-breaking customer turnout.

Case Installation

The Problem

BSM Construction required an experienced refrigeration contractor who could:

  • Begin work within a few weeks
  • Execute a full CO2 refrigeration system installation
  • Lay all the pipes and ensure proper insulation
  • Integrate Acorn Evac’s vacuum-based drainage system, eliminating conventional plumbing
  • Install, test and commission all cases, racks and EMS controls
  • Do whatever it takes to meet a non-negotiable opening date


The retailer did not move their opening dates. The general contractor needed a partner who could handle complexity, absorb lost time and coordinate daily with other trades.

CoolSys was the only partner with the scale, specialized CO2 expertise and operational speed required to execute successfully under these conditions.

Case Installation

The Solution

CoolSys mobilized just four weeks after award and delivered a complete, integrated refrigeration solution—including the entire Acorn Evac system installation.

Scope of Work Delivered

  • 3,100 ft of refrigeration piping installed and insulated
  • 28 Hill Phoenix refrigerated cases installed (medium + low temp) and commissioned
  • 1 CO2 rack installed, commissioned
  • Full Acorn Evac System installed, including vacuum lines, manifolds & case connections
  • Full building management system installation & calibration
  • All refrigerated cases EMS installation & calibration

Acorn Evac System Installation

The retailer used Acorn’s vacuum plumbing system for case drainage—eliminating the need for traditional plumbing trades. CoolSys self-performed the entire Acorn Evac installation, including:

  • Routing vacuum piping
  • Installing vacuum collection infrastructure
  • Ensuring proper drainage connections to every case
  • Integration with refrigeration piping drops
  • System testing, leak checks and final commissioning
Overhead Piping
Piping

Execution Excellence

CoolSys coordinated closely with BSM Construction and all trades, including:

  • Rephasing work as delays from other trades arose
  • Using all-terrain lifts to complete overhead piping before slab pours
  • Ensuring electricians had access to areas in the proper sequence
  • Using ProjectMates to document daily progress and support GC visibility

Accelerated Work

Whenever delays threatened the schedule, the CoolSys team accelerated work—often completing three weeks of installation in one week.

The Impact

CoolSys delivered a fully functional, finely tuned refrigeration environment—including the Acorn Evac system and full EMS controls—without a single delay to the store’s hard opening date.

Key Outcomes

  • Expert team deployment within weeks
  • Store opened on time as scheduled
  • Achieved one of the highest-attended grand openings for the retailer
  • CO2 rack and refrigeration systems performed flawlessly
  • Acorn Evac system operated reliably, enabling high-performance case drainage without traditional plumbing
  • EMS provided real-time visibility and control for both building systems and refrigerated cases
  • BSM Construction praised CoolSys for responsiveness, collaboration and ability to adapt to fast-moving field conditions
Piping Construction
Opening Day Line
Piping

Project Highlights

Refrigeration piping installed and insulated

0 ft

Hill Phoenix refrigerated cases installed (medium + low temp), started, tested and commissioned

0

CO2 rack installed, started, tested, and commissioned

0

Let's Discuss Your Next Project

If your project requires speed, precision and end-to-end refrigeration expertise, CoolSys is ready to deliver.

Related Reading

Preventive maintenance Industrial Refrigeration

Cold Storage CO2 Case Study

Cold Storage CO2 Case Study: how CoolSys turnkey engineering, installation, and maintenance solution reduced costs and emissions.

Refrigerated Case Upgrade Case Study: Multi-Store Conversion of Quick-Meal Case for Specialty Food Retailer

Supermarket | Multi-State Partial Remodel Refrigerated Cases Upgrade Across 150+ Stores Multi-Store Conversion of Quick-Meal Case for Specialty Food Retailer

CO2 Refrigeration Case Study: Yosemite Foods

Yosemite Foods Inc., in Modesto, CA, has been providing the highest quality specialty pork products to a diverse array of

Questions? Need Service?

We're Here to Help

Reach us directly for service requests at 866-417-6586, or fill out the form . Our team is ready to respond swiftly and answer any questions you may have.

Questions? Ready to Get Started?

Let’s Move Forward. Together.

Discover the advantages of aligning with the foremost authority in HVAC and refrigeration services. As a partner steeped in industry knowledge, we’re dedicated to elevating you, your team and your business. Learn More about our acquisition process and benefits, or fill out the form below.